Q2 FY27 investor presentation: 32.3 MTPA capacity, 50 MTPA target by FY30, project-wise costs
The update attaches the investor presentation that goes with the unaudited results for the quarter and half year ended September 30, 2026.
By ScoutQuest · · 2 min read
- Grey cement capacity
- 32.3 MTPA grey cement capacity
- Capacity roadmap
- 40 MTPA by FY28 and 50 MTPA by FY30
- Jaisalmer project cost
- ₹3,630 crore, with ₹1831 crore spent up to Sep-26
What was shared
The exchange update attaches the investor presentation that goes with the unaudited (standalone and consolidated) results for the second quarter and half year ended September 30, 2026, submitted by a separate letter dated October 24, 2026. The presentation covers company overview, business highlights, financial performance, ESG updates, and CSR and awards.
Scale of the business
- Grey cement capacity of 32.3 MTPA, which includes 0.42 MTPA in a subsidiary.
- White cement and wall putty capacity of 3.65 MTPA, which includes 0.60 MTPA in a subsidiary.
- About 91,000 dealers and retailers.
- Green power capacity of 342.3 MW, of which 223.0 MW is captive solar and wind.
- Waste heat recovery system of 119.3 MWh.
- Product portfolio spans grey cement, white cement, wall putty, tile adhesives and grouts, gypsum plaster, construction chemicals and paints.
Capacity roadmap
- Grey cement capacity has moved from 14.7 MTPA in 2021 to 24.3 MTPA in 2025 and 32.3 MTPA in 2026, each measured as of 31st March.
- The stated path is 40 MTPA by FY28 and 50 MTPA by FY30.
- The next 7 MTPA comes from a greenfield expansion at Jaisalmer and split grinding units at Bikaner and Bhatinda, to be commissioned by H1 FY28.
- A further 11 MTPA is planned through brownfield expansion at Muddapur and Panna.
Projects in progress and completed
- Jaisalmer, Rajasthan: 4 MTPA clinker and 3 MTPA cement capacity, project cost of ₹3,630 crore, with ₹1831 crore spent up to Sep-26 and commissioning scheduled for H1 FY28. Ordering and engineering are completed, and civil, mechanical and erection work is progressing as per schedule.
- Bikaner, Rajasthan: 2 MTPA split grinding unit, project cost of ₹565 crore, with ₹315 crore spent up to Sep-26 and commissioning scheduled for H1 FY28.
- Bhatinda, Punjab: 2 MTPA split grinding unit, project cost of ₹610 crore, with ₹108 crore spent up to Sep-26 and commissioning scheduled for H1 FY28. The presentation states that 100% land has been acquired, EC/CTE approvals are expected shortly, and major plant and equipment ordering is complete.
- Nathdwara, Rajasthan: a 6 lakh MT wall putty plant, project cost of ₹195 crore, with ₹160 crore spent up to Sep-26, commissioned on 12th Aug'26 with regular dispatches going on.
How a retail investor can use this
- The deck is the company's own account of its capacity, projects and progress, so it is best read alongside the reported numbers for the quarter.
- The costs versus spend figures show how much of each project is already funded and how much is left to be spent before the H1 FY28 commissioning dates.
- The roadmap from 32.3 MTPA today to 50 MTPA by FY30 is the long-term growth plan the company is tracking against.
Perception
A presentation of this kind generally reads as a routine, information-sharing update. The mix of a stated expansion roadmap, project-wise costs and a completed wall putty plant gives investors concrete markers to follow in coming quarters.
Also from JK Cement
Auditors certify covenant compliance; security cover at 3.76 times for listed NCDs
24 Oct 2026
Subsidiary to set up 75,000 KLPA water-based paint plant in Telangana at estimated cost of INR 130 Crore
24 Oct 2026
Board recommends Price Waterhouse Chartered Accountants LLP as statutory auditors for 5 years
24 Oct 2026
More numbers
- Grey cement capacity32.3 MTPA
- White cement and wall putty capacity3.65 MTPA
- Dealers and retailers~91,000
- Grey cement capacity target FY3050 MTPA
- Jaisalmer project cost₹3,630 crore
- Jaisalmer expenditure (YTD Sep-26)₹1831 crore
- Nathdwara wall putty plant capacity6 lakh MT
- Nathdwara wall putty plant project cost₹195 crore
Nothing here is a view, opinion or recommendation of ScoutQuest, its parent, directors or employees. ScoutQuest is a technology company: this page was assembled automatically from public sources using artificial intelligence, and may contain errors or omissions. Confirm everything against the original source before you act on it. Any use of this page is at your own risk, and neither ScoutQuest nor its parent, directors or employees accepts liability for it.