Receives Letter of Award for EPC Works of 200 MW / 500MWh Battery Energy Storage Project
Waaree Renewable Technologies has received a Letter of Award (LOA) for Engineering, Procurement and Construction (EPC) works of a Battery Energy Storage Project (BESS).
By ScoutQuest · · 2 min read
- Project Capacity
- 200 MW / 500MWh
- Work Scope
- Engineering, Procurement and Construction (EPC) works of a Battery Energy Storage Project (BESS)
- Completion Schedule
- financial year 2027-28
What was announced
Waaree Renewable Technologies Ltd has received a Letter of Award (LOA) for execution of Engineering, Procurement and Construction (EPC) works of a Battery Energy Storage Project (BESS). The company received the intimation of the Letter of Award on October 30, 2026 at 03:44 pm (IST).
Project details as stated
- Capacity: 200 MW / 500MWh
- Work scope: Engineering, Procurement and Construction (EPC) works of the battery energy storage project
- Awarding entity: a leading Independent Power Producer (IPP)
- The order has been awarded by a domestic entity and is a domestic order
- Nature of the order: Commercial Order
- Completion: the project is scheduled to be completed during the financial year 2027-28, as per the terms of the order
- The broad consideration or size of the order is stated as 200 MW / 500MWh
What is an EPC order, in simple words
Under an EPC contract, the company takes responsibility for the engineering (design), procurement (buying the equipment and materials) and construction of the project. In this case the project is a battery energy storage system, which stores electricity and releases it when needed. The company is the contractor executing the project for the entity that awarded the order.
Two numbers to note in the capacity
- 200 MW is the power rating, i.e. how much charge or discharge the system can handle at a point in time.
- 500MWh is the energy capacity, i.e. how much electricity the system can store in total.
Related party and interest checks
- The promoter / promoter group / group companies have no interest in the entity that awarded the order.
- The order does not fall within related party transactions.
How to read this
This is an order-win disclosure. It adds a battery energy storage EPC project to the company's order book, with the revenue linked to execution scheduled in financial year 2027-28. The awarding entity is described only as a leading Independent Power Producer, and the order size is stated in capacity terms of 200 MW / 500MWh.
Also from Waaree Renewable Technologies
Completed transfer of 100% shareholding in Waaree Green Data Centers to the holding company
30 Oct 2026
Q2 FY2027 call transcript: revenue up 36.53%, unexecuted order book above INR5,500 crore
28 Oct 2026
Receives LOA for 450 MWp solar EPC project, completion scheduled in FY2027-28
27 Oct 2026
More numbers
- BESS project capacity (power)200 MW
- BESS project capacity (energy)500MWh
- Order size as stated in Annexure A200 MW / 500MWh
Nothing here is a view, opinion or recommendation of ScoutQuest, its parent, directors or employees. ScoutQuest is a technology company: this page was assembled automatically from public sources using artificial intelligence, and may contain errors or omissions. Confirm everything against the original source before you act on it. Any use of this page is at your own risk, and neither ScoutQuest nor its parent, directors or employees accepts liability for it.