Addendum adds power plant and bricks unit details to Greenfield Steel Plant Terms of Reference intimation
Addendum to the intimation dated October 15, 2026 on fresh Terms of Reference (ToR) for a Greenfield Steel Plant.
By ScoutQuest · · 2 min read
- WHRB Power Plant Capacity
- 32 MW (Phase 1: 16 MW, Phase 2: 16 MW)
- FBC Power Plant Capacity
- 28 MW (Phase I: 8 MW, Phase 2: 20 MW)
- Bricks Manufacturing Unit Output
- Phase 1 24,000 bricks per day, Phase 2 40,000 bricks per day
Addendum to the ToR intimation
The company has shared an addendum to its intimation dated October 15, 2026, regarding the grant of fresh Standard Terms of Reference (ToR) by the Ministry of Environment, Forest and Climate Change (MoEF&CC), Government of India, on October 14, 2026, for the establishment of a Greenfield Steel Plant.
What this addendum adds
The company states that these details were inadvertently omitted from the brief details of the approval/license given in the earlier intimation, and that they form part of the project for which the fresh ToR has been granted by MoEF&CC.
- Power Plant (WHRB) - 32 MW: Phase 1 - 16 MW and Phase 2 - 16 MW
- FBC Power Plant - 28 MW: Phase I - 8 MW and Phase 2 - 20 MW
- Bricks Manufacturing Unit - Phase 1 (24,000 bricks per day) and Phase 2 (40,000 bricks per day)
What stays the same
Except for the above additions, all other details and disclosures contained in the earlier intimation dated October 15, 2026 remain unchanged. The company has asked the exchanges to take the information on record.
What a Terms of Reference is
In simple terms, a Terms of Reference (ToR) is the document in which the environment ministry's expert committee sets out the scope of studies and information a proposed project must prepare and submit. It is a step along the environmental clearance process rather than the clearance itself.
How to read this update
This is an addendum: it adds the power plant and bricks unit details that were left out of the earlier letter, and the rest of that earlier disclosure stands unchanged. The additional numbers describe the configuration of the proposed Greenfield Steel Plant project - power capacity in MW and bricks output per day - alongside the project already intimated.
Also from Vraj Iron And Steel
Addendum to fresh ToR intimation: 32 MW wHRB, 28 MW FBC power and brick units added
16 Oct 2026
Fresh Terms of Reference received from MoEF&CC for Greenfield Steel Plant project
15 Oct 2026
Board approves sale of entire 13.20% stake in MVK Industries to promoter for Rs. 4,55,40,000/-
28 Sep 2026
More numbers
- WHRB Power Plant capacity32 MW
- WHRB Power Plant Phase 1 capacity16 MW
- WHRB Power Plant Phase 2 capacity16 MW
- FBC Power Plant capacity28 MW
- FBC Power Plant Phase I capacity8 MW
- FBC Power Plant Phase 2 capacity20 MW
- Bricks Manufacturing Unit Phase 1 output per day24,000 Bricks per day
- Bricks Manufacturing Unit Phase 2 output per day40,000 Bricks per day
Nothing here is a view, opinion or recommendation of ScoutQuest, its parent, directors or employees. ScoutQuest is a technology company: this page was assembled automatically from public sources using artificial intelligence, and may contain errors or omissions. Confirm everything against the original source before you act on it. Any use of this page is at your own risk, and neither ScoutQuest nor its parent, directors or employees accepts liability for it.