Q2 FY27 production release: power sales 5593 Million Units, up 26% YoY; H1 10817 Million Units, up 32% YoY
- Total power sales Q2 FY27
- 5593 Million Units, up 26% YoY
- H1 FY27 power sales
- 10817 Million Units, up 32% YoY
- Meenakshi Energy sales
- +111% YoY
- Jharsuguda sales
- +186% YoY
- Sakti sales
- down 53% after a boiler incident, plant temporarily shut
Vedanta Power Limited released its production numbers for the quarter ended September 30, 2026.
Context given in the release
The company was demerged from Vedanta Limited during 1QFY27, so the quarter includes both pre- and post-demerger periods, and the release says comparisons with prior periods should be viewed accordingly. It also notes that in the first quarter of FY26 Meenakshi operated a single 300 MW unit, and that with full capacity (1,000 MW) operational, Q4 FY26 and H1 FY27 are presented on the expanded capacity base.
Power sales, in Million Units
- Total: 5593 in Q2 FY27 against 4433 in Q2 FY26, up 26%; 5224 in Q1 FY27, up 7% quarter on quarter
- H1 FY27: 10817 against 8217 in H1 FY26, up 32%
- Talwandi Sabo Thermal Plant: 2945 against 2789 in Q2 FY26, up 6%; H1 5668 against 5504, up 3%
- Meenakshi Energy Ltd: 1470 against 695 in Q2 FY26, up 111%; H1 2820 against 1086, up 160%
- Jharsuguda Thermal Plant: 873 against 305 in Q2 FY26, up 186%; H1 1559 against 983, up 59%
- Sakti Thermal Plant: 305 against 644 in Q2 FY26, down 53%; H1 769 against 644, up 19%
Plant availability
- Talwandi Sabo: 79% in Q2 FY27 against 90% in Q2 FY26; H1 83% against 90%
- Jharsuguda: 98% in Q2 FY27 against 43% in Q2 FY26; H1 95% against 55%
What the company highlighted
The release opens with "Record Sales Momentum at Vedanta Power: Q2 Sales Up 26% YoY to 5,593 Million Units, taking H1 Sales to a record 10,817 Million Units (+32% YoY)". It separately flags Meenakshi Energy's Q2 sales at 1,470 million Units, up 111% YoY and 9% QoQ, and Jharsuguda's Q2 sales at 873 million Units, up 186% YoY and 27% QoQ. Jharsuguda's Plant Availability Factor improved to 98% in Q2 FY27 compared with 43% in Q2 FY26.
Two operational points the release explains
- The TSTP PPA with the Punjab State Government compensates based on normative plant availability at 80%, and TSTP's availability for H1 stood well above 83%.
- The decline in power sales at Sakti Thermal Plant was primarily due to reduced plant availability following a boiler incident on April 14. The plant, formerly known as Athena Power Plant, is temporarily shut down since 14th April 2026 after the boiler blast in unit-I.
Scale of operations
The release states current installed capacity of 4.2 GW, with an additional 0.6 GW Shakti U2 under project phase, and lists a 1,980 MW plant in Mansa, Punjab; a 1,000 MW facility in Nellore, Andhra Pradesh; 1200 MW in Sakti, Chhattisgarh; and a 600 MW unit in Jharsuguda, Odisha.
More numbers
- Total power sales, Q2 FY27 (million units)5593
- Total power sales, H1 FY27 (million units)10817
- Total power sales, Q2 FY27 vs Q2 FY26 change26%
- Total power sales, H1 FY27 vs H1 FY26 change32%
- Meenakshi Energy Ltd power sales, Q2 FY27 (million units)1470
- Meenakshi Energy Ltd Q2 FY27 vs Q2 FY26 change111%
- Jharsuguda Thermal Plant power sales, Q2 FY27 (million units)873
- Jharsuguda Thermal Plant Q2 FY27 vs Q2 FY26 change186%
- Jharsuguda Thermal Plant availability, Q2 FY2798%
- Jharsuguda Thermal Plant availability, Q2 FY2643%
- Sakti Thermal Plant Q2 FY27 vs Q2 FY26 change-53%
- Current installed capacity4.2 GW
Nothing here is a view, opinion or recommendation of ScoutQuest, its parent, directors or employees. ScoutQuest is a technology company: this page was assembled automatically from public sources using artificial intelligence, and may contain errors or omissions. Confirm everything against the original source before you act on it. Any use of this page is at your own risk, and neither ScoutQuest nor its parent, directors or employees accepts liability for it.