Receives work order worth Rs. 19.4 crore from Hindustan Power Exchange for hardware, software and licences
Takyon Networks Ltd has received a work order from Hindustan Power Exchange Limited.
By ScoutQuest · · 1 min read
- Order Value
- Rs. 19.4 crore (Rupees Nineteen Crore Forty Lakh Only); the annexure states the size as NR 19.40 Crores
- Scope of Work
- supply of hardware, software and licenses
- Execution Timeline
- 60 days from the date of issuance of the Purchase Order (except Software & Licenses)
Order at a glance
- Takyon Networks Ltd has received a work order from Hindustan Power Exchange Limited.
- Value: Rs. 19.4 crore (Rupees Nineteen Crore Forty Lakh Only). The enclosed annexure states the size as NR 19.40 Crores.
- Scope of work: supply of hardware, software and licenses.
- Reference: Purchase Order No. HPX/IT/26-27/011 dated 23rd October 2026.
- The awarding entity is domestic, and the update describes the nature of the contract as a purchase order.
What the company disclosed
The annexure sets out the details in the format prescribed for order and contract disclosures. Beyond the order value and scope, it states that the order is to be executed within 60 days from the date of issuance of the Purchase Order, with software and licences excluded from that timeline.
Relationship with the awarding entity
- The promoter, promoter group and group companies have no interest in the entity that awarded the order.
- The order does not fall within related party transactions.
How to read this
This is a single purchase order from an exchange entity for supply of hardware, software and licences. For a reader tracking the company's business, the useful anchors are the Rs. 19.4 crore value and the 60-day execution window for the hardware portion, since that is the period over which the supplies covered by the timeline are to be completed.
The disclosure is informational: it records the receipt of the order and its broad terms, not the profit margin, payment schedule or per-item value split between hardware, software and licences.
Also from Takyon Networks
Receives work order worth ~Rs. 1.33 crore from Indian Institute of Technology, Kanpur
20 Oct 2026
Takyon Networks wins Rs. 2,56,10,953.77 work order from Banaras Locomotive Works, Indian Railways
7 Oct 2026
More numbers
- Order value (cover letter)Rs. 19,40,00,000/-
- Broad consideration or size of the orderNR 19.40 Crores
- Execution period for the order60 days
Nothing here is a view, opinion or recommendation of ScoutQuest, its parent, directors or employees. ScoutQuest is a technology company: this page was assembled automatically from public sources using artificial intelligence, and may contain errors or omissions. Confirm everything against the original source before you act on it. Any use of this page is at your own risk, and neither ScoutQuest nor its parent, directors or employees accepts liability for it.