Steamhouse India544914Capex expansion plan
Steamhouse India wins ₹311 crore EPC and 25-year O&M mandate for 300 TPH steam plant at Una Bulk Drug Park
By ScoutQuest · · 1 min read
1,005 TPHPotential platform capacity
Capacity under construction360 TPH
Capacity345 TPH
Steam plant capacity300 TPH
- Project Value
- ₹311 crore (inclusive of GST)
- Steam Plant Capacity
- 300 TPH
- Co-generation Capacity
- 30 MW
- EPC Timeline
- 24 months from commencement
- O&M Mandate
- 25-year
Steamhouse India wins ₹311 crore EPC and 25-year O&M mandate for 300 TPH steam plant at Una Bulk Drug Park.
Also from Steamhouse India
Steamhouse India to hold Q2 FY27 earnings call on October 30, 2026 at 1:00 PM IST
19 Oct 2026
Board meeting on 29 October 2026 to approve September quarter and half-year results
19 Oct 2026
Steamhouse India cancels Investors & Analysts Plant Visit set for 23 October 2026
16 Oct 2026
More numbers
- Order value₹311 crore (inclusive of GST)
- Steam plant capacity300 TPH
- Co-generation power capacity30 MW
- EPC completion period24 months
- O&M period25 years
- Existing capacity345 TPH
- Capacity under construction360 TPH
- Potential platform capacity1,005 TPH
Source: BSE · 24 Sep 2026
Nothing here is a view, opinion or recommendation of ScoutQuest, its parent, directors or employees. ScoutQuest is a technology company: this page was assembled automatically from public sources using artificial intelligence, and may contain errors or omissions. Confirm everything against the original source before you act on it. Any use of this page is at your own risk, and neither ScoutQuest nor its parent, directors or employees accepts liability for it.