Q1 FY27 earnings call transcript: steam capacity to rise from 345 to 705 tons per hour; new Una EPC mandate

Transcript of Steamhouse India's maiden earnings call on Q1 FY27 (quarter ended June 30, 2026).

90.7%Share of revenue from repeat customers
Share of revenue from repeat customers: 90.7%.
Steam Distribution Capacity
rising from 345 to approximately 705 tons per hour
Una EPC Project Value
about INR311 crores inclusive of GST
Nitrogen Plant Capacity
350 Nm3 per hour started at Ankleshwar

What the transcript covers

Steamhouse India has shared the transcript of its maiden earnings call, held on October 6, 2026, on its unaudited financial results (standalone and consolidated) for the quarter ended June 30, 2026. The management on the call was Chairman and Managing Director Vishal S. Budhia and Chief Financial Officer Vaibhav Gattani. The company noted it was in a silent period pending the announcement of its results for the quarter ended September 30, 2026, and that the discussion was limited to information already in the public domain. Management described the quarter as a strong one for the company despite a challenging macroeconomic environment.

The business model in brief

Expansion pipeline

Entry into Himachal Pradesh

Nitrogen and fuel mix

What investors can track

Nature of the call

Management's remarks on future capacity, projects and new verticals are forward-looking statements based on current beliefs, opinions and expectations, and are not a guarantee of future performance. The call was limited to information already in the public domain.

More numbers
  • Share of FY26 revenue from repeat customers90.7%
  • Customers served21 customers
  • Steam pipeline infrastructure in Gujaratmore than 60 kilometers
  • Current steam distribution capacity345 tons per hour
  • Expected steam distribution capacity after initiativesapproximately 705 tons per hour capacity
  • EPC mandate project value at Bulk Drug Park, UnaINR311 crores
  • Community boiler facility capacity at Una300 tons per hour
  • Nitrogen PSA plant capacity at Ankleshwar350 Nm3 per hour
Source: BSE · 10 Oct 2026

Nothing here is a view, opinion or recommendation of ScoutQuest, its parent, directors or employees. ScoutQuest is a technology company: this page was assembled automatically from public sources using artificial intelligence, and may contain errors or omissions. Confirm everything against the original source before you act on it. Any use of this page is at your own risk, and neither ScoutQuest nor its parent, directors or employees accepts liability for it.