Board Comments On Exchange Fines For Board And Committee Composition Gaps (Q1 FY27)
NSE and BSE levied fines on REC for non-compliance with Board and committee composition norms for the quarter ended June 30, 2026.
- Total Fine Payable
- Rs. 1077340 (basic Rs. 913000 + GST Rs. 164340)
- Fine for Board Composition
- Rs. 5,000 per day for 91 days, basic fine Rs. 455000
- Fine for Audit Committee
- Rs. 2,000 per day for 82 days, basic fine Rs. 164000
- Fine for Board Quorum
- Rs. 10,000 per instance for 3 instances, basic fine Rs. 30000
- Board Noted Date
- September 19, 2026
What happened
NSE (letter) and BSE (email), both dated August 25, 2026, flagged REC's non-compliance with SEBI LODR requirements on the composition of the Board and its committees for the quarter ended June 30, 2026, and levied fines.
Fine break-up as computed by the exchanges
- Regulation 17(1), Board composition: Rs. 5,000 per day for 91 days, basic fine Rs. 455000
- Regulation 18(1), audit committee: Rs. 2,000 per day for 82 days, basic fine Rs. 164000
- Regulation 19(1)/19(2), nomination and remuneration committee: Rs. 2,000 per day for 66 days, basic fine Rs. 132000
- Regulation 20(2)/(2A), stakeholders relationship committee: Rs. 2,000 per day for 66 days, basic fine Rs. 132000
- Regulation 17(2A), quorum of Board meetings: Rs. 10,000 per instance for 3 instances, basic fine Rs. 30000
- Total basic fine 913000, GST @18% 164340, total payable 1077340
Board's comments
The matter was placed before the Board on September 19, 2026. The Board noted the non-compliance and the fines, and desired regular follow-up with the appointing authority, the Ministry of Power, Government of India, to expedite appointment of the requisite number of Independent Directors.
Company's position
REC states that as a Government Company, and per its Articles of Association, the power to appoint Independent Directors rests with the President of India acting through the Ministry of Power, and the Company has no role in director appointments. On that basis it has requested that the fines imposed be waived off.
Points investors may note
- The exchange letters state fines keep accruing daily until compliance is achieved.
- The exchange communication notes that failure to pay within 15 days can lead to action on freezing promoter shareholding, and a second consecutive quarter of non-compliance under certain regulations can lead to transfer to Z group and liability for suspension of trading.
- Waiver applications require compliance as a pre-requisite, with non-refundable processing fees of Rs.10,000 plus 18% GST.
- The underlying cause cited is the pending appointment of Independent Directors by the Government.
Also from REC
Three power transmission companies incorporated as wholly owned subsidiaries
6 Oct 2026
Viewer holding REC at a loss asked whether to hold or exit; experts recommend hold/buy with targets
30 Sep 2026
Sale and Transfer of Project-Specific SPV Balsane Power Transmission Completed
28 Sep 2026
More numbers
- Total fine payable (inclusive of GST)1077340
- Total basic fine913000
- GST @18% on fine164340
- Reg 17(1) fine per day5000
- Reg 17(1) days of non-compliance91
- Reg 17(1) fine amount455000
- Reg 18(1) days of non-compliance82
- Reg 18(1) fine amount164000
- Reg 19(1)/19(2) fine amount132000
- Reg 20(2)/(2A) fine amount132000
- Reg 17(2A) instances3
- Reg 17(2A) fine amount30000
Nothing here is a view, opinion or recommendation of ScoutQuest, its parent, directors or employees. ScoutQuest is a technology company: this page was assembled automatically from public sources using artificial intelligence, and may contain errors or omissions. Confirm everything against the original source before you act on it. Any use of this page is at your own risk, and neither ScoutQuest nor its parent, directors or employees accepts liability for it.