ScoutQuest22 Oct 2026
Petronet LNG532522JV deal update

Binding term sheet signed with Gruner Renewable Energy for a CBG joint venture

Petronet LNG signed a binding term sheet on 22 October 2026 with Gruner Renewable Energy Private Limited to form a joint venture company.

By ScoutQuest · · 1 min read

Planned JV Plants
10 CBG plants
Capacity per Plant
18 MT per day
Estimated Capital Outlay
Rs. 1,200 crore

What was signed

What the joint venture will do

The plan in numbers

How the JV is structured

Other points disclosed

What a retail investor may note

More numbers
  • Estimated capital outlay for the JV's CBG plantsRs. 1,200 crore
  • Number of CBG plants planned by the JV company10
  • Capacity of each CBG plant18 MT per day
  • Equity participation split between the two partners50:50
Source: BSE · 22 Oct 2026

Nothing here is a view, opinion or recommendation of ScoutQuest, its parent, directors or employees. ScoutQuest is a technology company: this page was assembled automatically from public sources using artificial intelligence, and may contain errors or omissions. Confirm everything against the original source before you act on it. Any use of this page is at your own risk, and neither ScoutQuest nor its parent, directors or employees accepts liability for it.