Turbine-Generator Order Placed for 1,600 MW Phase-II of Salboni Thermal Project
JSW Thermal Energy (wholly owned subsidiary) has contracted associate company Toshiba JSW for two 800 MW steam turbine generators for Phase 2 of the Salboni Thermal Project, West Bengal.
- Turbine-Generator Contract
- Two 800 MW steam turbine generators for Phase 2 of Salboni Thermal Project
- Total Project Capacity
- 3,200 MW (4 x 800 MW) with all TG orders now placed
- Under-construction Capacity
- 5,000 MW comprising 3,200 MW at Salboni and 1,800 MW at JSW Mahanadi Power Company Limited
- Total Locked-in Generation Capacity
- 32.4 GW (15.0 GW operational and 13.4 GW under construction, plus 4.0 GW pipeline)
- 2030 Target Capacity
- 30 GW of generation capacity and 40 GWh of energy storage
What was announced
JSW Thermal Energy Limited, a wholly owned subsidiary of JSW Energy, has entered into a contract with Toshiba JSW Power Systems Private Limited, an associate company, for procurement of two steam turbine generators of 800 MW each for Phase 2 of the Salboni Thermal Project in West Bengal.
With this order, turbine-generator equipment orders for the entire 3,200 MW (4 x 800 MW) Salboni Thermal Power Project are complete, following the earlier Phase 1 (2 x 800 MW) order.
Why the company says it matters
- The TG package will be manufactured and supplied in line with the project's construction schedule.
- Sourcing through an associate company is aimed at supply-chain certainty and better coordination during execution.
- The company cites industry-wide equipment shortages as a risk it seeks to reduce.
Capacity context shared
- Installed thermal generation capacity: 5,958 MW.
- Under-construction capacity: 5,000 MW, comprising 3,200 MW at Salboni and 1,800 MW at JSW Mahanadi Power Company Limited.
- Total locked-in generation capacity: 32.4 GW, being 15.0 GW operational and 13.4 GW under construction, with a pipeline of 4.0 GW.
- Locked-in energy storage: 29.6 GWh, comprising 26.4 GWh pumped hydro and 3.2 GWh battery storage.
Stated targets
The company is targeting 30 GW of generation capacity and 40 GWh of energy storage by 2030, and carbon neutrality by 2050.
How investors may read it
The disclosure indicates equipment procurement milestones for a large thermal project being locked in, involving a related associate company. Forward-looking statements in the release carry the usual execution and market risks noted by the company.
Also from JSW Energy
Installed capacity reaches 15,147 MW; 1,694 MW added since April 2026
5 Oct 2026
NCLT sanctions GE Power India and JSW Energy Scheme of Arrangement
1 Oct 2026
More numbers
- Phase II turbine-generator capacity ordered1,600 MW
- Size of each steam turbine generator800 MW
- Total Salboni Thermal Power Project capacity3,200 MW (4 x 800 MW)
- Installed thermal generation capacity5,958 MW
- Under construction capacity5,000 MW
- Under construction capacity at JMPCL1,800 MW
- Total locked-in generation capacity32.4 GW
- Operational capacity15.0 GW
- Under construction capacity (locked-in)13.4 GW
- Locked-in energy storage capacity29.6 GWh
- Target generation capacity by 203030 GW
- Target energy storage by 203040 GWh
Nothing here is a view, opinion or recommendation of ScoutQuest, its parent, directors or employees. ScoutQuest is a technology company: this page was assembled automatically from public sources using artificial intelligence, and may contain errors or omissions. Confirm everything against the original source before you act on it. Any use of this page is at your own risk, and neither ScoutQuest nor its parent, directors or employees accepts liability for it.