Installed capacity reaches 15,147 MW; 1,694 MW added since April 2026
Total installed capacity is now 15,147 MW after adding 1,694 MW since April 2026, including ~1.4 GW of renewables.
- Total installed capacity
- 15,147 MW
- Capacity added since April 2026
- 1,694 MW, including ~1.4 GW of renewables
- Renewables share of operational portfolio
- ~61% (9,189 MW)
- Thermal portfolio
- 5,958 MW
- FY27 renewable addition target progress
- ~46% of the FY27 renewable addition target of 3 GW
What the company informed the exchanges
The company has added 1,694 MW of installed generation capacity since April 2026, including about 1.4 GW of renewable capacity. With this, total installed capacity stands at 15,147 MW.
Where the new capacity came from
- 593 MW of solar
- 108 MW of wind
- 542 MW of hybrid
- 150 MW of hydro
- 300 MW of inorganic thermal capacity of Maruti Clean Coal & Power Ltd
How the operational portfolio looks now
- Renewable energy is about 61% of the operational portfolio, at 9,189 MW
- Within renewables: 3,125 MW wind, 2,426 MW solar, 1,857 MW hybrid and 1,781 MW hydro
- Thermal portfolio: 5,958 MW
Progress against the stated target
- The company's FY27 renewable capacity addition target is 3 GW
- It states it has already delivered approximately 46% of that targeted capacity
- The CEO's comment notes 1.4 GW of renewable capacity commissioned in the first half of FY27, with the balance 1.6 GW to be delivered during the year, and says land, transmission connectivity and equipment supply for the remaining capacity are already in place
What else the release sets out
- Total locked-in generation capacity of 32.4 GW, comprising 15.1 GW operational and 14.5 GW under construction across thermal, hydro and renewables, plus a pipeline of 2.8 GW
- Locked-in energy storage capacity of 29.6 GWh, comprising 26.4 GWh of pumped hydro storage and 3.2 GWh of battery energy storage
- Stated targets of 30 GW of generation capacity and 40 GWh of energy storage by 2030, and carbon neutrality by 2050
How a reader can look at it
- The update is a progress report on capacity build-out: it shows how much has been added this financial year and how the operational fleet is now split between renewables and thermal
- It also gives the company's own measure of progress against its FY27 addition target and restates longer-term capacity and storage goals
- The release includes forward-looking statements, which the company notes involve risks and uncertainties, so the stated targets and the CEO's comments about the balance capacity are projections rather than completed events
What to keep in mind
- The figures here are about installed and locked-in capacity, which describes the size of the generation fleet and project pipeline, not the electricity actually generated or sold in the period
Also from JSW Energy
NCLT sanctions GE Power India and JSW Energy Scheme of Arrangement
1 Oct 2026
Turbine-Generator Order Placed for 1,600 MW Phase-II of Salboni Thermal Project
25 Sep 2026
More numbers
- Total installed capacity after additions15,147 MW
- Capacity added since April 20261,694 MW
- Renewable capacity added since April 2026~1.4 GW
- Solar capacity added in FY27 to date593 MW
- Wind capacity added in FY27 to date108 MW
- Hybrid capacity added in FY27 to date542 MW
- Hydro capacity added in FY27 to date150 MW
- Inorganic thermal capacity of Maruti Clean Coal & Power Ltd300 MW
- Renewable share of operational portfolio~61%
- Renewable operational capacity9,189 MW
- Thermal portfolio5,958 MW
- Capacity under construction14.5 GW
Nothing here is a view, opinion or recommendation of ScoutQuest, its parent, directors or employees. ScoutQuest is a technology company: this page was assembled automatically from public sources using artificial intelligence, and may contain errors or omissions. Confirm everything against the original source before you act on it. Any use of this page is at your own risk, and neither ScoutQuest nor its parent, directors or employees accepts liability for it.