Additional 1.00 MTPA grinding unit commissioned at Nagaur; total installed grinding capacity now 25.10 MTPA

JSW Cement has commissioned an additional 1.00 MTPA cement grinding unit at its Nagaur plant in Rajasthan.

New Grinding Unit
additional 1.00 MTPA cement grinding unit at its Nagaur plant in Rajasthan
Total Installed Grinding Capacity
25.10 MTPA
Total Clinker Manufacturing Capacity (incl. JV)
9.74 MTPA

What was announced

The Nagaur plant

Other systems commissioned

How to read this

Context on the company

More numbers
  • Additional cement grinding unit commissioned at Nagaur1.00 MTPA
  • Total installed cement grinding capacity after commissioning25.10 MTPA
  • Total clinker manufacturing capacity, including JV9.74 MTPA
  • Nagaur clinkerisation unit capacity3.30 MTPA
  • Nagaur cement grinding unit capacity before the addition2.50 MTPA
  • Nagaur plant total cement grinding capacity after the addition3.50 MTPA
  • Market share in GGBS salesapproximately 84%
Source: BSE · 6 Oct 2026

Nothing here is a view, opinion or recommendation of ScoutQuest, its parent, directors or employees. ScoutQuest is a technology company: this page was assembled automatically from public sources using artificial intelligence, and may contain errors or omissions. Confirm everything against the original source before you act on it. Any use of this page is at your own risk, and neither ScoutQuest nor its parent, directors or employees accepts liability for it.