1.50 MnTPA pellet plant: financial closure achieved, all existing lenders approve the Rs. 720.00 crore project
Financial closure achieved for the new 1.50 MnTPA Straight-Grate Pellet Plant at Siltara, Raipur; all existing lenders have approved it.
- Appraised Project Cost
- ~Rs. 720.00 crore
- Sanctioned Term Debt
- Rs. 540.00 crore
- Equity & Internal Accruals
- Rs. 180.00 crore
- Construction Period
- 24 months from first term debt drawdown
- New Plant Capacity
- 1.50 MnTPA Straight-Grate Pellet Plant
Pellet capacity addition moves to the funding stage
The company already operates a pellet plant of 1.5 MnTPA, running at utilisation of around 90%. It proposes to add a new 1.50 MnTPA Straight-Grate Pellet Plant, along with a new Raw Material Handling System and other associate facilities, within its Integrated Steel Plant Complex at Siltara, Raipur (Chhattisgarh).
What the company has disclosed
- It has achieved financial closure for the said project.
- It has received approval from all its existing lenders for the project.
Money and how it is funded
- Appraised Project Cost: around Rs. 720.00 Crores
- Sanctioned Term Debt: Rs. 540.00 Crores
- Equity & Internal Accruals: Rs. 180.00 Crores
Timeline
- Construction period of 24 Months, commencing from the date of first drawdown of the Term Debt, which is yet to materialise.
Why the company says it is doing this
- A crucial business expansion, using iron ore from the captive iron ore mines.
How a retail investor can read this
Financial closure plus lender approval is the point at which the funding structure for a project is tied up. In this case, roughly three-fourths of the appraised cost is sanctioned term debt, with the rest coming from equity and internal accruals.
The capacity itself is yet to be built. The 24-month construction clock begins only when the first tranche of the Term Debt is drawn, and that drawdown is yet to happen. Treated as a plan, this would add one more pellet plant of the same size as the existing one, fed by captive iron ore.
Also from Jayaswal Neco Industries
Jayaswal Neco Industries Ltd promoter buys 2.26% stake
6 Oct 2026
Board approves appointment of Rana Das as President (Materials Management), designated Senior Management Personnel
1 Oct 2026
Allotment of 2,24,39,134 Warrants on Preferential Basis at INR 89.13 Each
1 Oct 2026
More numbers
- Existing pellet plant capacity1.5 MnTPA
- Existing capacity utilisationAround 90%
- Proposed capacity addition1.50 MnTPA
- Construction period for proposed capacity24 Months
- Appraised Project CostAround Rs. 720.00 Crores
- Sanctioned Term DebtRs. 540.00 Crores
- Equity & Internal AccrualsRs. 180.00 Crores
Nothing here is a view, opinion or recommendation of ScoutQuest, its parent, directors or employees. ScoutQuest is a technology company: this page was assembled automatically from public sources using artificial intelligence, and may contain errors or omissions. Confirm everything against the original source before you act on it. Any use of this page is at your own risk, and neither ScoutQuest nor its parent, directors or employees accepts liability for it.