Fujiyama Power Systems544613Capex expansion plan
Clarification on China solar cell tech export curbs: plant machinery already delivered, timeline unchanged
Fujiyama Power Systems says machinery for its announced 1.2 GW DCR solar cell plant at Ratlam, Madhya Pradesh is already delivered.
By ScoutQuest · · 1 min read
- Solar cell plant capacity
- 1.2 GW DCR solar cell plant
- Plant location
- Ratlam, Madhya Pradesh
- Commissioning timeline
- Q1 FY2027-28
What the update says
- It is a clarification to recent media reports about China's proposed restrictions on the export of technologies and machinery used in solar cell manufacturing.
- The company states that the machinery and equipment required for its announced 1.2 GW DCR (Domestic Content Requirement) solar cell manufacturing facility have already been delivered to its plant at Ratlam, Madhya Pradesh.
Impact on the project as stated by the company
- It does not anticipate any material impact of the proposed restrictions on the capital expenditure or the timeline of this expansion.
- The facility remains on track to be commissioned as originally planned, in Q1 of FY 2027-28.
- At this stage, the company has not announced any plans for additional solar cell manufacturing capacity.
- The company states its operations are not dependent on any ongoing foreign technology transfer and remain fully unaffected.
How this fits the business
- The company is in the retail-focused rooftop solar business, manufacturing and supplying Solar Power Generation Systems (SPGS) made up of solar inverters, solar batteries and solar panels.
- Solar panel making is a backward integration of that business, and solar cell manufacturing is a further backward integration for solar panel manufacturing.
The takeaway
- The update addresses a specific worry, that export curbs by a major supplier country could delay or raise the cost of a planned factory. The company's answer is that the equipment it needs is already at site.
- The stated checkpoints to track are the stated capital expenditure and the commissioning window of Q1 FY 2027-28 for the 1.2 GW facility.
Also from Fujiyama Power Systems
Fujiyama Power rose 3% after the company said China curbs will not impact its solar cell project, but the stock later turned negative and analysts recommended staying away
22 Oct 2026
Fujiyama Power's board approved an enabling resolution to raise funds via the QIP route
16 Oct 2026
Board approves QIP of up to Rs. 1,200 crore, allots 4,11,587 ESOP shares
15 Oct 2026
More numbers
- Announced DCR solar cell manufacturing capacity1.2 GW
Source: BSE · 21 Oct 2026
Nothing here is a view, opinion or recommendation of ScoutQuest, its parent, directors or employees. ScoutQuest is a technology company: this page was assembled automatically from public sources using artificial intelligence, and may contain errors or omissions. Confirm everything against the original source before you act on it. Any use of this page is at your own risk, and neither ScoutQuest nor its parent, directors or employees accepts liability for it.