Epack Prefab Technologies544540New project launch
Commercial production commenced at Ghiloth, Rajasthan plant; PEB and PUF panel capacity added
Commercial production at the Ghiloth, Rajasthan plant began October 28, 2026, after the pollution board's Consent to Operate.
By ScoutQuest · · 2 min read
- Capacity Added - PEB
- 11,300 Metric Tons/Annum
- Capacity Added - PUF Panels
- 8,00,000 Square Meters/Annum
- Investment
- around INR 100 Crore, from IPO net proceeds
What the company announced
- EPACK Prefab Technologies has commenced commercial production of Pre-Engineered Buildings (PEB) structures and PUF panels at its Ghiloth Facility, located at Plot No. SP3-257, RIICO Industrial Area, Ghiloth, Tehsil Neemrana, District Kotputli-Behror, Rajasthan.
- The commencement date is October 28, 2026.
- The Rajasthan State Pollution Control Board granted its Consent to Operate for the facility vide its Order dated October 28, 2026.
Capacity before and after
- Existing PEB structures capacity: 1,47,122 Metric Tons/Annum.
- Existing PUF panel capacity: 13,10,000 Square Meters/Annum.
- Capacity added at the facility: 11,300 Metric Tons/Annum for PEB structures and 8,00,000 Square Meters/Annum for PUF panels.
- Existing capacity utilisation was around 77.50% for PEB structures and around 49.50% for PUF panels.
Money and funding
- Investment required: around INR 100 Crore.
- Mode of financing: net proceeds of the IPO.
Why the company says it is doing this
- The stated rationale is to cater to the growing demand for PEB structures and PUF panels in North India.
How to read this
- This is an operational update: a new manufacturing line has moved from being set up to actually producing and selling output.
- Installed capacity is the maximum the company can produce; utilisation tells you how much of the old capacity was already being used. The PEB side was running at around 77.50%, while PUF panels were at around 49.50%.
- The money for this expansion is described as coming from IPO net proceeds, so the update links the spend to funds already raised rather than to a fresh borrowing.
- The PEB addition of 11,300 Metric Tons/Annum and the PUF addition of 8,00,000 Square Meters/Annum are the incremental volumes the company says it can now make.
- Whether this translates into higher sales depends on demand actually materialising, which the update addresses only through the stated rationale of North India demand.
- The consent to operate from the state pollution board is the regulatory clearance that allows the plant to run.
Also from Epack Prefab Technologies
Commercial production begins at Ghiloth plant; PEB and PUF capacity added
28 Oct 2026
EPack Prefab to hold Q2FY27 earnings conference call on November 4, 2026 at 4:30 PM IST
28 Oct 2026
Board meeting on November 2, 2026 to approve September quarter and half-year results
26 Oct 2026
More numbers
- Existing PEB structures capacity1,47,122 Metric Tons/Annum
- Existing PUF panel capacity13,10,000 Square Meters/Annum
- Existing PEB capacity utilisationAround 77.50%
- Existing PUF capacity utilisationAround 49.50%
- PEB structures capacity addition11,300 Metric Tons/Annum
- PUF panel capacity addition8,00,000 Square Meters/Annum
- Investment requiredAround INR 100 Crore
Source: BSE · 28 Oct 2026
Nothing here is a view, opinion or recommendation of ScoutQuest, its parent, directors or employees. ScoutQuest is a technology company: this page was assembled automatically from public sources using artificial intelligence, and may contain errors or omissions. Confirm everything against the original source before you act on it. Any use of this page is at your own risk, and neither ScoutQuest nor its parent, directors or employees accepts liability for it.