Diamond Power to add CCV line for cables up to 132 kV at Vadodara, investing Rs 25 crore
Diamond Power Infrastructure Ltd will add a Catenary Continuous Vulcanisation (CCV) line for cables up to 132 kV at its Vadodara plant, targeting commissioning by 31 December 2027.
By ScoutQuest · · 1 min read
- Investment
- Rs 25 crore
- Target Commissioning
- 31 December 2027
- Existing Capacity Utilisation
- 60%
- Release
- Launch / capacity
🏭 The machinery is scheduled for delivery by August 2027, and the line is targeted for commissioning by 31 December 2027.
🏭 With the addition, DICABS will operate Six CCV lines LO & Five Silane Lines at its 130-acre single-location plant.
🏭 The company prints its existing EHV cable capacity at about 2,000 km a year and existing capacity utilisation at 60%.
📋 Mr Kavish Shah, Vice President, said the company's EHV order book is growing steadily and customers are asking for larger volumes on shorter timelines.
Also from Diamond Power Infrastructure
CFO appointed from October 20; outgoing CFO re-designated Deputy CFO, not a resignation
19 Oct 2026
Board approves new Chief Financial Officer; Pawan Lohiya re-designated Deputy CFO
19 Oct 2026
CFO change: Kundip S. Thakker appointed CFO, Pawan Lohiya re-designated Deputy CFO
19 Oct 2026
More numbers
- Investment required, new CCV lineRs 25 crore
- Existing capacity utilisation60%
- Existing EHV cable capacity~2,000 km p.a.
- Proposed capacity addition, new CCV lineOne CCV line, up to 132 kV p.a.
Nothing here is a view, opinion or recommendation of ScoutQuest, its parent, directors or employees. ScoutQuest is a technology company: this page was assembled automatically from public sources using artificial intelligence, and may contain errors or omissions. Confirm everything against the original source before you act on it. Any use of this page is at your own risk, and neither ScoutQuest nor its parent, directors or employees accepts liability for it.