Completion Certificate received for ₹1,659.84 crore Delhi–Saharanpur Highway stretch

Completion Certificate received for the 16.85-km, six-lane NH-709B stretch from the Delhi/UP Border to the Eastern Peripheral Expressway Junction.

By ScoutQuest · · 2 min read

Revised estimated project cost
₹1,659.84 crore
O&M per annum
₹2.88 crore per annum, plus escalation
Fit for operation from
September 12, 2024

The company has received a Completion Certificate from the Authority's Engineer for a key stretch of the Delhi–Saharanpur Highway in Uttar Pradesh, executed jointly with Gayatri Projects Limited. The certificate is dated October 12, 2026.

What has been certified

Project size and scope

What the company will do next

Timeline of the contract

What the management said

About the company

How a reader can look at this

More numbers
  • Length of certified highway stretch16.85-km
  • Revised estimated project cost₹1,659.84 crore
  • Operation & Maintenance fee per annum₹2.88 crore
  • Cure period after extended completion date30-day
  • Lanes on the certified stretchsix-lane
  • EPC expertiseover 24 years
  • States where projects are executed13 states
Source: BSE · 13 Oct 2026

Nothing here is a view, opinion or recommendation of ScoutQuest, its parent, directors or employees. ScoutQuest is a technology company: this page was assembled automatically from public sources using artificial intelligence, and may contain errors or omissions. Confirm everything against the original source before you act on it. Any use of this page is at your own risk, and neither ScoutQuest nor its parent, directors or employees accepts liability for it.