Further Delay in Commissioning of 9.9 MW Hybrid Power Project; Phased Schedule Now Runs to December 2026
Borana Weaves has reported a further delay in its 9.9 MW Hybrid Power Project at Kalikanagar, Gujarat.
- Project Capacity
- 9.9 MW Hybrid Power Project
- Solar Component
- 7.65 MW
- WTG 1 + Solar Expected Completion
- end-October 2026
- WTG 2 Expected Completion
- end-November 2026
- WTG 3 Expected Completion
- end-December 2026
What was announced
Borana Weaves informed the exchanges of a further delay in commissioning its 9.9 MW Hybrid Power Project at Kalikanagar, Gujarat. This follows an earlier intimation dated 29 August 2026 on the same project.
Revised timeline
- One WTG (wind turbine generator) location along with the 7.65 MW solar component: earlier expected by 30 September 2026; commissioning activities have not commenced as on date and are now expected by end-October 2026.
- Second WTG location: earlier end-October 2026, now expected by end-November 2026.
- Third WTG location: earlier end-October 2026, now expected by end-December 2026.
Reasons given
- High wind speeds halting WTG erection.
- Heavy monsoon at site, requiring rework of the logistics road.
- Delay in obtaining timely shutdown of the existing 33 kV and 11 kV lines needed for the 33 kV transmission-line work.
The company states these are factors beyond the control of the Company and the project developer. A confirming letter from the project developer, Clean Max Enviro Energy Solutions Limited, accompanies the intimation and sets out the same revised dates.
How investors may read it
The project is a captive/renewable power initiative rather than the core weaving operation, so the immediate effect is on the timing of expected power-cost savings rather than on current manufacturing capacity. This is the second successive revision to the schedule, which readers may view as execution slippage, though the stated causes are weather and utility-shutdown approvals.
More numbers
- Hybrid power project capacity9.9 MW
- Solar component capacity7.65 MW
- WTG locations remaining after first phasetwo WTG locations
Nothing here is a view, opinion or recommendation of ScoutQuest, its parent, directors or employees. ScoutQuest is a technology company: this page was assembled automatically from public sources using artificial intelligence, and may contain errors or omissions. Confirm everything against the original source before you act on it. Any use of this page is at your own risk, and neither ScoutQuest nor its parent, directors or employees accepts liability for it.