Colour Coating Line commissioned at Bokaro, marking first phase of Greenfield Downstream Steel Complex

BMWIL has commissioned the Colour Coating Line at its Bokaro Greenfield Downstream Steel Complex — the first phase of the project.

₹341.6 croreTotal capital deployed towards the project as on 30th June
Debt drawdown of the deployed capital₹202.4 crore
Internal accruals of the deployed capital₹139.2 crore
Total capital deployed towards the project as on 30th June ₹341.6 crore: Debt drawdown of the deployed capital ₹202.4 crore, Internal accruals of the deployed capital ₹139.2 crore.
Total project cost
₹803 crore
Capital deployed as on 30th June 2026
₹341.6 crore
Revenue commencement expected
Q3 FY27
Debt tied up
₹500 crore from a consortium led by SBI, HDFC Bank and Yes Bank
Commissioned asset
Colour Coating Line at Bokaro Greenfield Downstream Steel Complex

BMW Industries Ltd has commissioned the Colour Coating Line at its Greenfield Downstream Steel Complex at Bokaro, Jharkhand. The company describes this as the first phase of the complex and a step in its transition from a conversion-led business to an integrated, value-added downstream steel player.

What has been commissioned

Funding

Capacities planned for the complex

Energy

Timeline

What the company says

Chairman Mr. Ram Gopal Bansal said the commissioning of the Colour Coating line is an important first step in the greenfield expansion, that the Bokaro complex will allow control of the chain from Hot Rolled to Coated products, and that it will offer the complete basket of coated steel while diversifying the product mix and customer base. He also referred to industry tailwinds for value-added and coated steel, supportive government policy and disciplined capital deployment, with focus on ramping up the facility.

How to read this

More numbers
  • Total project cost of the Greenfield Downstream Steel Complex at Bokaro₹803 crore
  • Total capital deployed towards the project as on 30th June 2026₹341.6 crore
  • Internal accruals of the deployed capital₹139.2 crore
  • Debt drawdown of the deployed capital₹202.4 crore
  • Capitalised towards the Colour Coating line as on 5th October 2026₹60 crore
  • Debt tied up from consortium led by SBI, HDFC Bank and Yes Bank₹500 crore
  • Planned Cold Rolled Full Hard (CRFH) capacity550,000 TPA
  • Planned GA/GI/ZAM capacity540,000 TPA
Source: BSE · 5 Oct 2026

Nothing here is a view, opinion or recommendation of ScoutQuest, its parent, directors or employees. ScoutQuest is a technology company: this page was assembled automatically from public sources using artificial intelligence, and may contain errors or omissions. Confirm everything against the original source before you act on it. Any use of this page is at your own risk, and neither ScoutQuest nor its parent, directors or employees accepts liability for it.