ScoutQuest25 Sep 2026
Adani Power533096Deal

NCLT Mumbai sanctions merger of Vidarbha Industries Power; both benches have now approved the Scheme

NCLT Mumbai, by order dated September 24, 2026, sanctioned the amalgamation of wholly owned subsidiary Vidarbha Industries Power Limited with Adani Power.

By ScoutQuest · · 2 min read

NCLT Approval Date
September 24, 2026
Appointed Date of Scheme
April 1, 2025
VIPL Thermal Power Capacity
600 MW (2 units of 300 MW each)
Adani Power Total Operational Capacity
14,550 MW
Subsidiaries Merged
Ten wholly owned subsidiaries consolidated

What happened

The National Company Law Tribunal, Mumbai Bench, pronounced an order on 24.09.2026 sanctioning the amalgamation of Vidarbha Industries Power Limited (VIPL), a wholly owned subsidiary, with Adani Power Limited. The order was uploaded on the NCLT website on September 25, 2026.

Earlier, NCLT Ahmedabad had sanctioned the same Scheme on August 4, 2026 for the nine other wholly owned subsidiaries: Adani Power Dahej, Kutchh Power Generation, Resurgent Fuel Management, Mahan Fuel Management, Orissa Thermal Energy, Korba Power, Anuppur Thermal Energy (MP), Mirzapur Thermal Energy (UP) and Emberiza Infra Park. With the Mumbai order, the Scheme has the requisite approvals from both benches.

Timing

The Appointed Date of the Scheme is April 1, 2025. The Scheme will be effective upon completion of the steps laid out in it, and the company will update the exchanges then.

Consideration

All transferor companies are wholly owned (VIPL is directly held; Kutchh Power Generation is held by Adani Power Dahej). The shares held by Adani Power and its nominees stand cancelled and extinguished, with no allotment of equity shares in Adani Power. So there is no dilution for existing shareholders.

The entities involved

Capital position as on March 31, 2026

Stated rationale

The boards of VIPL and Adani Power approved the Scheme by resolutions passed on 30th October 2025. Since the merger is of wholly owned subsidiaries into the holding company, a no-objection letter from the stock exchanges was not required under Regulation 37 of SEBI LODR; the Scheme was shared with the exchanges for disclosure.

More numbers
  • VIPL thermal plant capacity600 MW
  • VIPL units2 units of 300 MW each
  • Adani Power total operational capacity14,550 MW
  • VIPL paid-up equity shares1,00,000 equity shares of Rs.10/- each
  • VIPL paid-up capital amount10,00,000
  • Adani Power paid-up equity shares1928,46,94,705 equity shares of Rs. 2/- each
  • Adani Power paid-up equity capital3856,93,89,410
  • Adani Power preference shares4,15,86,207 Preference Shares of Rs. 100/- each
  • Number of transferor companies(i) to (x)
Source: BSE · 25 Sep 2026

Nothing here is a view, opinion or recommendation of ScoutQuest, its parent, directors or employees. ScoutQuest is a technology company: this page was assembled automatically from public sources using artificial intelligence, and may contain errors or omissions. Confirm everything against the original source before you act on it. Any use of this page is at your own risk, and neither ScoutQuest nor its parent, directors or employees accepts liability for it.