Phase-III of BESS Project Commissioned — 53.63 MW/214.52 MWh in Rajasthan
Phase-III of the BESS component commissioned: 53.63 MW/214.52 MWh out of 300 MW/1200 MWh of the FDRE project at Bikaner, Rajasthan, on September 30, 2026.
- Phase-III BESS Capacity Commissioned
- 53.63 MW/214.52 MWh
- Total Project Capacity
- 300 MW/1200 MWh
- Cumulative Commissioned BESS Capacity
- 159.58 MW/638.32 MWh
- Commissioning Date
- September 30, 2026
- Commercial Operation Date (COD)
- October 02, 2026
What was announced
ACME Solar Holdings, through its wholly owned subsidiary ACME Greentech Seventh Private Limited, has commissioned Phase-III of the Battery Energy Storage System (BESS) component of its FDRE project.
- Phase-III capacity commissioned: 53.63 MW/214.52 MWh
- Part of a total of 300 MW / 1200 MWh (discharge capacity)
- Location: Village Kelan, Tehsil Chhatargarh, District Bikaner, Rajasthan
- Commissioned on September 30, 2026; Commercial Operation Date (COD) will be October 02, 2026
- Cumulative commissioned BESS capacity at this subsidiary: 159.58 MW/638.32 MWh
- Power Purchase Agreement signed with SJVN Limited
Why it matters
FDRE stands for Firm and Dispatchable Renewable Energy — projects that pair renewable generation with storage so power can be supplied on a firm schedule. Battery storage lets the project store energy and release it when required under the agreement.
Commissioning followed by a commercial operation date means the capacity can begin supplying power under the long-term PPA, which is the point at which revenue from that capacity typically begins.
This update continues an earlier intimation dated September 17, 2026, and represents progress on a phased build-out, with the remaining portion of the 300 MW/1200 MWh discharge capacity still to be commissioned.
Also from ACME Solar Holdings
ICRA AA- (Stable) reaffirmed on ACME Solar Holdings; rated amount raised to Rs. 3,500.00 crore
7 Oct 2026
ACME Solar Holdings incorporates 18 wholly owned renewable energy subsidiaries at Rs. 1,00,000 each
6 Oct 2026
Additional 66.68 MW solar capacity commissioned; hybrid project now at 133.36 MW of 300 MW
5 Oct 2026
More numbers
- Phase-III BESS capacity commissioned (MW)53.63 MW
- Phase-III BESS energy commissioned (MWh)214.52 MWh
- Total project BESS discharge capacity (MW)300 MW
- Total project BESS discharge energy (MWh)1200 MWh
- Cumulative commissioned BESS capacity (MW)159.58 MW
- Cumulative commissioned BESS energy (MWh)638.32 MWh
Nothing here is a view, opinion or recommendation of ScoutQuest, its parent, directors or employees. ScoutQuest is a technology company: this page was assembled automatically from public sources using artificial intelligence, and may contain errors or omissions. Confirm everything against the original source before you act on it. Any use of this page is at your own risk, and neither ScoutQuest nor its parent, directors or employees accepts liability for it.