ScoutQuest1 Oct 2026
ACME Solar Holdings544283Capex expansion plan

Phase-III of BESS Project Commissioned — 53.63 MW/214.52 MWh in Rajasthan

Phase-III of the BESS component commissioned: 53.63 MW/214.52 MWh out of 300 MW/1200 MWh of the FDRE project at Bikaner, Rajasthan, on September 30, 2026.

214.52 MWhPhase-III BESS energy commissioned (MWh
Cumulative commissioned BESS capacity (MW159.58 MW
Phase-III BESS capacity commissioned (MW53.63 MW
Phase-III BESS energy commissioned (MWh 214.52 MWh: Cumulative commissioned BESS capacity (MW 159.58 MW, Phase-III BESS capacity commissioned (MW 53.63 MW.
Phase-III BESS Capacity Commissioned
53.63 MW/214.52 MWh
Total Project Capacity
300 MW/1200 MWh
Cumulative Commissioned BESS Capacity
159.58 MW/638.32 MWh
Commissioning Date
September 30, 2026
Commercial Operation Date (COD)
October 02, 2026

What was announced

ACME Solar Holdings, through its wholly owned subsidiary ACME Greentech Seventh Private Limited, has commissioned Phase-III of the Battery Energy Storage System (BESS) component of its FDRE project.

Why it matters

FDRE stands for Firm and Dispatchable Renewable Energy — projects that pair renewable generation with storage so power can be supplied on a firm schedule. Battery storage lets the project store energy and release it when required under the agreement.

Commissioning followed by a commercial operation date means the capacity can begin supplying power under the long-term PPA, which is the point at which revenue from that capacity typically begins.

This update continues an earlier intimation dated September 17, 2026, and represents progress on a phased build-out, with the remaining portion of the 300 MW/1200 MWh discharge capacity still to be commissioned.

More numbers
  • Phase-III BESS capacity commissioned (MW)53.63 MW
  • Phase-III BESS energy commissioned (MWh)214.52 MWh
  • Total project BESS discharge capacity (MW)300 MW
  • Total project BESS discharge energy (MWh)1200 MWh
  • Cumulative commissioned BESS capacity (MW)159.58 MW
  • Cumulative commissioned BESS energy (MWh)638.32 MWh
Source: BSE · 1 Oct 2026

Nothing here is a view, opinion or recommendation of ScoutQuest, its parent, directors or employees. ScoutQuest is a technology company: this page was assembled automatically from public sources using artificial intelligence, and may contain errors or omissions. Confirm everything against the original source before you act on it. Any use of this page is at your own risk, and neither ScoutQuest nor its parent, directors or employees accepts liability for it.