Phase-I BESS of 53.73 MW/222.969 MWh Commissioned at Rajasthan FDRE Project
ACME Solar's wholly-owned arm ACME Sigma Urja has commissioned Phase-I of the BESS component — 53.73 MW/222.969 MWh out of 250 MW/1069 MWh — at its FDRE project in Chittorgarh, Rajasthan.
- Phase-I BESS Capacity Commissioned
- 53.73 MW/222.969 MWh
- Total BESS Discharge Capacity
- 250 MW/1069 MWh
- Project Location
- Village Neemri, Chittorgarh, Rajasthan
- Commercial Operation Date
- October 02, 2026
- Subsidiary
- ACME Sigma Urja Private Limited
What was announced
ACME Solar Holdings, through its wholly-owned subsidiary ACME Sigma Urja Private Limited, has commissioned Phase-I of the Battery Energy Storage System (BESS) component of its FDRE (Firm and Dispatchable Renewable Energy) project.
Capacity details
- Phase-I commissioned: 53.73 MW / 222.969 MWh
- Total BESS discharge capacity of the project: 250 MW / 1069 MWh
- Location: Village Neemri, Tehsil Rawatbhata, District Chittorgarh, Rajasthan
- Commissioning date: September 30, 2026
- Commercial operation date (COD): October 02, 2026
What this means
An FDRE project combines renewable generation with storage so that power can be supplied on a firm, schedulable basis. Here only the storage portion has gone live in part; the company states the corresponding renewable energy generation component is under development. Capacity turning commercially operational is the point from which a project can begin contributing revenue, subject to the applicable arrangements.
The commissioned Phase-I represents a portion of the project's full storage capacity, with the balance still to be commissioned.
Also from ACME Solar Holdings
ICRA AA- (Stable) reaffirmed on ACME Solar Holdings; rated amount raised to Rs. 3,500.00 crore
7 Oct 2026
ACME Solar Holdings incorporates 18 wholly owned renewable energy subsidiaries at Rs. 1,00,000 each
6 Oct 2026
Additional 66.68 MW solar capacity commissioned; hybrid project now at 133.36 MW of 300 MW
5 Oct 2026
More numbers
- Phase-I BESS capacity commissioned (MW)53.73 MW
- Phase-I BESS energy commissioned (MWh)222.969 MWh
- Total project BESS capacity (MW)250 MW
- Total project BESS discharge capacity (MWh)1069 MWh
Nothing here is a view, opinion or recommendation of ScoutQuest, its parent, directors or employees. ScoutQuest is a technology company: this page was assembled automatically from public sources using artificial intelligence, and may contain errors or omissions. Confirm everything against the original source before you act on it. Any use of this page is at your own risk, and neither ScoutQuest nor its parent, directors or employees accepts liability for it.